ARMOUR WELDING ON THE CHURCHILL TANK MARK VII

 

The inception of the Churchill tank dates from the opening stages of the war, when a tank was required for coping with the Siegfried Line defences. Preliminary designs were in course of preparation when France was overrun and England was faced with the possibility of invasion. The Churchill tank as it finally appeared, therefore, was designed to fight in the English countryside.

 

The Churchill tank Mark 1 was armed with a 2‑pdr. gun, a coaxial 7.92 mm. Besa machine gun in the turret and a 3 in. howitzer in the hull by the side of the driver. In the Mark II tank the howitzer was replaced by a second 7.92 mm. Besa machine gun, the two machine guns being retained on all subsequent Marks. The turret was cast and the hull was of riveted double‑skin construction with 3.5 in. frontal armour and 2.5 in. side armour, both superimposed on a 0.5 in. mild‑steel or high‑tensile‑steel lining. Experience in the early stages of the North African campaign led to the substitution of a 6‑pdr. gun for the 2‑pdr. and later, for the European campaign, the tank with which this bulletin is primarily concerned, the " heavy” Churchill Mark V11 was developed, mounting a 75 mm. gun. This tank has a composite cast and plate turret of welded construction and a single‑skin welded hull with frontal armour on a 6 in. basis and side‑armour of 3.75 in. All armour plate is to I.T. 80 specification and the turret casting to I.T. 90 specification.

 

The Churchill Mark VII weighs‑nearly 40 tons and measures 24 ft. 2 in. long, 10 ft. 10 in. wide over air‑inlet louvers; 9 ft. 5 in. over sandguards and 9 ft. 0 in. high over the No. 9 aerial base. The air‑inlet louvres are detachable to bring the overall width of the vehicle within railway loading gauge.

 As with all previous Marks, it is manned by a crew of five, consisting of a commander, gunner and loader in the turret and a driver and machine-gunner in the hull. The engine is a Bedford Twin 12‑cylinder, horizontally opposed unit developing 340 b.h.p. at 2,200 r.p.m. It drives through a David Brown, four‑speed constant‑mesh, gearbox, giving a maximum road speed of 31 m.p.h. Steering is on the controlled differential system. The suspension is peculiar to the Churchill, and consists of eleven spring bogies on each side of the tank, engaging the lower run of the track by means of flanged wheels of comparatively small diameter. Side panniers are incorporated in the tank hull and the bogies are bolted underneath the panniers; the tops of the panniers being fitted with skid rails to carry the returning top halves of the tracks. Damage to one bogie does not materially upset the suspension, and the damaged bogie can be replaced without disturbing any other part.

 

The Churchill tank has gained an excellent reputation in the fields in which it has been employed, and it was widely used for the mounting of certain of the special devices required for the European invasion. The designer of the Churchill tank was Vauxhall Motors Ltd., who assumed their responsibilities in July 1940. A welded Churchill Mark V11 is illustrated in Fig. 1, and a Mark VIII, which is similar except that it is armed with a 95 mm howitzer, in Fig. 2.

 

THE WELDED CHURCHILL

When the Churchill was initially designed the possibility of welded con­struction was considered seriously but little was then known of the perform­ance of heavy welded armour construction in battle and immediate production was a paramount necessity. It was decided that the risk could not then be taken. Nevertheless this did not preclude experimental development, and the first welded mock‑up in heavy armour plate was submitted to firing trial in July 1940,with highly satisfactory results. This mock‑up was built by Babcock & Wilcox Ltd., who were appointed technical parents on the welded development by Vauxhall Motors Ltd. In November 1940; Babcock & Wilcox Ltd. were given an order for an experimental Churchill Mark IV welded hull and, an order for a second, similar hull in January 1941.

 

It was about this time that the decision was made to arm the Churchill with a 6‑pdr. gun and as this required a larger turret than the cast one then in use, it was decided that this change provided a suitable opportunity for introducing welded construction in production. Accordingly, in May 1941, Babcock & Wilcox Ltd. were asked to construct a welded turret for firing trial, and subsequently 21 further experimental turrets were ordered from a number of representative firms and using plates supplied by several different steel makers. The firing trial on the Babcock & Wilcox turret took place in July 1941, and the results were so favourable that a production order for 100 turrets was placed with Babcock & Wilcox Ltd. forthwith (August 1941). Firing trials continued to be conducted on the other experimental turrets as they became available, and the results confirmed the wisdom of the decision to adopt welded construction.

 

At this time a discussion was proceeding as to the necessity for postheating welded armour structures in order to relieve welding stresses and temper the heat‑affected zones; and advantage was taken of the turret programme to investigate the matter. The original Babcock & Wilcox experimental turret had been postheated, so the first of the production turrets ordered from this firm was made to precisely the same procedure but without postheating and, in October 1941, was submitted to an exactly similar firing trial. The comparative results showed that postheating was unnecessary, but to confirm the point, five of the 21 further experimental turrets were fired-at in the non‑postheated condition, and the results not only supported the original conclusion but disclosed the danger that subsequent postheating might actually degrade the ballistic quality of the armour plates.

 

 At the same period, a parallel investigation was in progress on the experimental hulls. The first of these hulls was approaching completion and was postheated, but in the case of the second hull postheating was omitted. The two hulls were built into tanks and subjected to 1,500 miles rough‑usage running, after which the non‑postheated hull was stripped and submitted to firing trial in July 1942. These trials confirmed the conclusion that postheating was unnecessary, and provided ample evidence that the welding of heavy tank hulls was sound policy. To put the matter beyond doubt, a Mark IV riveted hull was submitted to a similar firing trial, and although it behaved well for a riveted structure, the correctness of the decision to weld heavy armour was unchallenged.

 

In all this early work the joints were pre-coated with 25:20 electrodes, a practice that it was possible later to discontinue. In the meantime, a comparison between riveted and welded construction had been made from the production angle. An analysis was made by the Department of Tank Design, in collaboration with the contractors concerned between the current production data on riveted Mark IV hulls, built by The Whessoe Foundry, & Engineering Co. Ltd., Darlington, and Metropolitan‑Cammell Carriage and Wagon Co. Ltd., Old Park Works, Wednesbury; and the welded prototypes built by Babcock & Wilcox Ltd.

 

In a report prepared by the Welding and Gas Cutting Branch in March 1942, it was concluded that welding would save 20 per cent. in man‑hours and 4 per cent. in weight, as compared with riveting but required 50 per-cent more floor space in the fabricator's works.  This additional floor space would be largely counterbalanced by a reduction in space required at the plate maker's works, due to the greatly reduced amount of drilling required. The additional floor space was, therefore, not regarded as a serious drawback in the circumstances but the savings in labour and material were vital considerations. Subsequent experience showed that a greater saving in welding man‑hours was effected than had been estimated and the allowance for floor space had been over‑generous.

 

 By the time the foregoing investigations were completed, the demand had arisen for the "heavy" Churchill, and it was decided that the Mark VII tank should be of welded construction. To assist in obtaining the necessary production the contract was extended to certain other firms, including The Whessoe Foundry & Engineering Co. Ltd., Newton Chambers & Co. Ltd., and the Gloucester Railway Carriage & Wagon Co. Ltd.

 

As a result of further development work, Babcock & Wilcox Ltd. abandoned the practice of pre-coating and adopted a particular technique of horizontal vertical welding that came to be known as “flat‑bead” welding. This method was employed for all the experimental structures with which they had been concerned and, on the basis of the firing trials, was accepted by the Department of Tank Design for production.  At a later date The Whessoe Foundry & Engineering Co. Ltd. introduced a gravity welding technique on the Churchill hull, as far as the jigs and manipulators would permit and they were subsequently followed, with modifications, by Gloucester Railway & Carriage Wagon Co. Ltd. and Newton Chambers & Co. Ltd. Gravity welding with large‑gauge electrodes (i.e. five sixteenths and three eights in. diameter) was by then the accepted practice for all other types of tank construction and offered certain advantages, economic and otherwise.

 

As already mentioned, in designing the turret for the Mark VII vehicle to take the 75‑mm. gun, a composite cast and welded construction was decided upon. For the main structure of a turret a casting possesses the advantages over a welded structure in that the thickness of sections can be varied as desired, and turret can be contoured more efficiently so that weight is saved. On the other hand, if the roof and floor are cast integral with the turret structure, they would have to be thicker than necessary so as to avoid extreme changes of section in the casting. The construction most economical was therefore a cast turret with rolled roof and floor plates welded-in and this was the construction adopted for the Mark VII turret.

 

MANUFACTURING PROCEDURE

When the additional contractors were introduced they adopted jigs and manipulators to Babcock & Wilcox designs, and followed the manufacturing procedure adopted by that firm. Subsequently, in certain details, each contractor developed methods or equipment to suit his own convenience and the adoption of gravity welding has, of course, involved an important departure in procedure. The retention of existing equipment, which was the obviously correct course from the standpoint of maintaining production, imposed a certain limitation in exploiting gravity welding fully. We shall, therefore, describe the manufacturing procedure as carried out at the works of Babcock & Wilcox Ltd. referring to departures made by other contractors as they arise in the course of the description.

 

PLATE  PREPARATION

All contractors receive plate ready-profiled, mainly by gas cutting but all edges to be welded have to be dressed before the plates are assembled. The dressing operation is carried out by portable grinders, flame de-scaling and wire brushing,

 

HULL

For purposes of manufacture the hull is divided into the following sub-assemblies: floor, side panniers, nose and roof. The rear end is built up and two outer idler plates added during the main assembly and the engine‑compartment roof forms a separate sub‑assembly.

 

FLOOR

The floor sub‑assembly consists of a 25 mm. plate under driver and fighting compartments, a 20 mm. plate under the engine compartment, 2.25‑in. side members and four cross members, the whole being built up in a trunnion‑mounted jig. When the tank hull comes to be assembled it is lined up on longitudinal and transverse centre lines passing through the axis of rotation of the turret and in building the floor, the first operation is to place the bottom plates on the jig, line them up, and mark longitudinal and transverse centre lines passing through a hole drilled on the centre point of the turret. This operation is shown in Fig. 3. The plates are then clamped and the transverse butt-joint between welded.

In the next stage, the side members are introduced and welded, as shown in Fig. 4. The outside welds for these members have to be interrupted where they pass beneath the clamps, and are completed after the assembly has been removed from the jig. To avoid this, the Gloucester Railway Carriage & Wagon Co. Ltd. merely tack the assembly in the jig and then transfer it to a manipulator, depicted in Fig. 5, which enables the welds to be deposited complete in the gravity position.

 

Finally, the four cross members, which are mild‑steel fabrications, are welded in position (see Fig. 6), tapping pads are welded around the inspection holes, inspection covers fitted, and sundry minor items added.

 

SIDE PANNIERS

The first stage in the construction of a side pannier is the welding of the nose as a separate sub‑assembly; an operation which is carried out in the jigs seen in Fig. 7. At Whessoe Foundry & Engineering Co. Ltd. these jigs are not used, the nose being built up as described later in this paragraph. The pannier itself is built up in a rotary manipulator which is shown partly plated in Fig. 8, and with the nose added in Fig. 9. At the Whessoe works, the two nose plates are placed temporarily in position on the pannier against a template and tacked, after which they are removed and the inside weld is deposited. The nose is then returned to the pannier assembly for welding in position; the outside weld of the nose being deposited in the manipulator. This procedure enables both inside and outside welds on the nose to be laid down in the gravity position whereas the Babcock jigs are designed for horizontal‑vertical welding.

 

After the main carcase of the pannier has been welded, bulkhead plates are fixed and a number of ferrules, bosses and other attachments are located by simple fixtures and welded (see Fig. 10). Amongst these fixtures are pairs of key plates for the reception of special devices. The distance between these plates has to be held to an accuracy of 0.020 in. and each contractor has developed his own jig attachment for fitting them. Each design depends on a plate with machined faces for setting the key plates to exact distance but, as will be seen from Figs. 11‑14, the methods of clamping the key plates differs considerably.

 

Fig. 11 also shows the type of fixture used by Newton Chambers &Co. Ltd. for welding the pannier‑door hinge brackets. This is a precision operation, and the methods adopted are of some interest. The machined taper of the door­ opening is placed face upwards, checked for out-of-round caused by the welding of the top and bottom plates and adjusted by grinding until the door beds down to the required depth and clearance limits. The outside faces and the side plates, in the vicinity of the hinge location, are now ground level and the hinge assembly, consisting of two straps extending over the door, and four hinge blocks seating on the side plate, is threaded on a master pin and laid in position.  Shims are then placed under the door straps to bring them to correct height, and the straps are fastened to the door by set screws. Shims are now fitted between the hinge blocks and the side plate until the blocks bed firmly and swing freely on the hinge pin.

 

 The clamping fixture seen in Fig. 12 is now placed in position and is secured by being hooked under the pannier top plate on one side, and bolted to the bogie suspension holes on the other. Hinge blocks and straps are now welded, the master pin removed and two permanent pins fitted. Final adjustment of the door does not take place until the hull is nearly completed, thus avoiding the danger of the hinges being strained by the door violently opening when the hull is tilted during assembly. (see also Fig. 13 and Fig. 14)

 

As already mentioned, skid rails are attached to the pannier tops to carry the return run of the track. In view of the heavy wear to which these rails are subjected, their attachment created something of a problem. Originally they were secured to the pannier tops by bolts with countersunk heads, but the heads wore away with the track abrasion and the rails came adrift before their useful life was ended. Furthermore, the nuts; being on the inside of the pannier, could not easily be reached when it was desired to remove the rails. A proposal was then made to weld the rails to the panniers, but the rails were made of silico‑manganese steel which was difficult to weld, inclined to be brittle and could develop cracks. Eventually this welding problem was overcome by pre-coating the rails with 25:20 electrodes and by welding only around the ends, leaving the centre of the rail free instead of employing staggered intermittent welds, as had previously been done.

 

NOSE

The main nose assembly consists of visor, glacis, and nose plates, and the inner idler‑support brackets. It is built up and welded in a trunnion jig as seen in Fig. 15, after which it is removed from the jig, and a towing eye and certain other fittings are added. Those contractors who have adopted gravity welding take advantage of this trunnion jig to deposit the heavy transverse welds on this assembly in the gravity position. Accurate fitting is required for the visor door and because the hinge straps are welded to the door, care must be taken to prevent the pull of the welds from throwing the assembly out of register. Babcock & Wilcox Ltd. overcame this difficulty by welding the straps to the door in a block jig, whereas Whessoe Foundry & Engineering Co. Ltd. and Gloucester Railway, Carriage and Wagon Co. Ltd. fit the door to the visor plate before the nose is assembled, as shown in Fig. 16. Babcock & Wilcox Ltd. and Newton Chambers & Co. Ltd. fit the visor door after the hull has been completed.

 

ROOF PLATE AND ENGINE‑COMPARTMENT ROOF

These assemblies call for little comment. The roof‑plate sub‑assembly jig is seen plated up on the right of Fig. 17 and a completed roof plate is in the centre. Originally, the frames for the roof doors were bolted‑on units, as are seen stacked along the front of Fig. 17 but more recently, the hinges and splash strips have been welded directly to the roof. The engine‑compartment roof is a simple framework carrying four, access doors. It is built up in a jig similar to that used for the roof plate.

 

MAIN HULL ASSEMBLY

The hulls are assembled in rotary manipulators. Babcock & Wilcox Ltd. are equipped with twelve, Newton Chambers & Co. Ltd. with ten (Figs. 18 and 19), and Whessoe Foundry & Engineering Co. Ltd. and Gloucester Railway Carriage & Wagon Co. Ltd. with seven each.

 

Operations are commenced by seating the floor assembly in the lower half of the manipulator and following it with the panniers which are lined up fore and aft on the transverse centre line marked on the floor assembly and set to gauge distance apart along the longitudinal centre line. This stage is seen in Fig. 20. The main nose is then fitted (Fig. 21) and the entire assembly is lined up with a straight edge and plumb bob, then held with screw jacks extending between the panniers as seen in Fig. 22. This stage of the assembly is then welded. Fig. 23 depicts a hull in this stage at Gloucester Railway Carriage & Wagon Co. Ltd. and shows the use by that firm of a screw jack to give an outward preset to the inner idler brackets. Fig. 24, taken at the same works, shows a hull in this stage positioned for gravity welding.

 

Fabrication continues by insertion of the upper side members, followed by the bulkheads. In connection with the upper side members, an interesting departure is made by Newton Chambers & Co. Ltd. The members are laid on the floor in a locating fixture which holds them in their exact relative positions, then the top half of the manipulator cage is lowered over them and they are bolted to the cage as seen in Fig. 25. Thus, when the cage is closed after the insertion of the panniers, the upper side members are offered to the assembly in their correct relative positions. Incidentally, this procedure includes these structures in the first‑stage assembly.

 

The assembly of the rear end of the hull is an operation calling for considerable accuracy, as the alignment of the drive is dependant on it. The structure comprises an inner and outer pair of drive plates connected by end plates and the apertures in these drive plates must be truly concentric as well as on an axis at right angles to the centre line of the hull. To do this, a jig frame is built up, locating on the bogie bracket holes, and carrying the drive plates by their apertures on spigots. This frame is seen in course of construction in Fig. 26. A cross beam is laid inside the rear ends of the panniers and is bolted to them through the bolt-holes for the rear bogie brackets. A longitudinal frame is then bolted to this beam, giving the stage shown in Fig. 26. Side members to which the drive plates have already been fixed are then bolted to this frame, as seen in Fig .27. Fitted bolts are used throughout to ensure that all parts of the jig frame register accurately. Brackets attached to the jig frame provide seatings for the rear plates which are now fitted as shown in Fig. 28. After the rear end has been welded, the jig frame is removed and the rear sloping plate inserted in position and welded.

 

Variants of the foregoing procedure have been introduced by Newton Chambers & Co. Ltd. and by the Whessoe Foundry & Engineering Co. Ltd. Newton Chambers builds up the jig frame, complete with drive plates, independently of the hull, as in Fig. 29, then offer it to the hull as a unit. At the Whessoe Works, the rear unit is completed to the rear plates, as seen in Fig. 30,  with rear sloping plate being laid in position before the rear unit is offered up. This operation is completed before the manipulator is closed and before any main welding is carried out on the hull. These variants are stated to save several hours of plating time. Concurrently, with the fitting of the rear end, the roof plate is fitted as depicted in Fig. 31. All parts of the structure added since the first‑stage welding are now welded up.

 

The final operation in the manipulator is the fitting of the outer idler plates. These must be in accurate alignment with the inner idler plates, and they are jigged as shown in Fig. 32. Each outer plate is held in register with the corresponding inner plate by a dumbbell-shaped fixture having rectangular spigots at the ends that engage the jaws of the plates. Slotted distance-bars are also laid over the plates to hold them parallel. Fig. 33 shows the same stage at the Whessoe Works. The manipulator in this instance being positioned for gravity welding on the hull in accordance with the procedure adopted by that firm.

 

The hull is now removed from the manipulator to receive the finishing operations (see Fig. 34). Amongst these, an interesting item is the fixing of the gearbox and engine bearing pads, which have to be positioned accurately with regard to both one another and to the centre line of the final drive. At the Whessoe Works this is carried out by the jig shown in Fig. 35 which not only locates the pads in correct alignment with the final drive, but ensures that they are in correct vertical register with one another, thus allowing for any warping or unevenness of the floor.

 

Turret

As already stated, the turret is a casting with welded top and bottom plates. Operations are commenced by buffing the bottom plate and then aligning it to receive the traverse‑gear bracket which will be welded in place next. The plate is then marked out for centre lines and laid in position in the turret casting which has been previously buffed to receive it. To locate the plate, a fixture is registered on the back and sides of the gun‑mounting aperture and carries a trammel by which the hole in the bottom plate is set truly central. The plate is then clamped and welded. Fig. 36 shows the plate ready for welding. Certain reinforcing members are then set on the inside of the bottom plate and welded.

 

The top of the turret consists of two plates which are connected by a transverse weld across the centre of the turret. Precautions must be taken to prevent the plates bellying downwards after welding. After buffing and drilling the plates are fitted over a restraining support, as seen in Fig. 37, which gives an upward preset of three-eighths of an inch when the plates are clamped down. The loader's door-drain-channel, cupola ring, aerial bases and smoke‑mortar boss are then added to complete the turret which finally appears as seen in Fig. 38.

 

Turrets are also made by the Whessoe Foundry & Engineering Co. Ltd., a group of turrets under construction at these works being seen in Fig. 39. The most important difference in procedure as compared with that at Babcock & Wilcox Ltd. lies in the treatment of the top plates which are clamped to a faceplate as seen in Fig. 40 and welded before they are offered to the casting.

 

Sandguards

Figs. 41 and 42 show the manufacture of sandguards by the Gloucester Welding Co. Ltd. (branch of Thos. Ash & Co. Ltd., Birmingham) who are subcontractors to the Gloucester Railway Carriage and Wagon Co. Ltd. The guards are of mild‑steel sheet and are assembled in sections using wooden Jigs, then spot welded as seen in Fig. 41. The completed sections are then fitted together on the steel formers seen in Fig. 42 and the construction completed by arc welding.

 

Final Assembly

Of the four main contractors already mentioned, Newton Chambers & Co. Ltd. and the Gloucester Railway Carriage & Wagon Co. Ltd. produce completed tanks and views of the final assembly lines at these two works are given in Fig. 43 and Fig. 44. The other contractors send their hulls and turrets to Vauxhall Motors Ltd., Charles Roberts & Co. Ltd., and Dennis Bros. Ltd. for final assembly.

 

Abbreviations key:

B&W:                          Babcock & Wilcox

GRC&W                     Gloucester Railway Carriage & Wagon

NC                              Newton Chambers

VM                              Vauxhall Motors

WF                              Whessoe Foundry & Engineering

 

END